Owner Guide · Updated November 2026

NYC Sidewalk Shed Rules 2026

90-day permit renewals, RDP progress reports, DOB fees and penalties under the “Get Sheds Down” laws: what building owners need to know, and how to keep a shed permit renewal on track.

Sidewalk shed along a New York City building facade
Related ResourcesSidewalk Shed RDP Inspections →CD-5 Suspended Scaffold Design →DOB Rule 1 RCNY §102-07 ↗

2026 Rules at a Glance

Permit termSidewalk shed permits now last 90 days and no longer renew automatically in DOB NOW.
Renewal reportA Registered Design Professional (P.E. or R.A.) must document the progress of the repair work.
Fees$130 renewal fee, plus a $90 progress report fee where a report is required.
LawsLocal Laws 48 and 51 of 2025 (effective January 12, 2026) and DOB rule 1 RCNY §102-07.

What Changed for Sidewalk Sheds

For years, a sidewalk shed permit could simply be renewed each year while the shed stayed up and little work happened behind it. The “Get Sheds Down” package changed that. Local Laws 48 and 51 of 2025 took effect on January 12, 2026, cutting shed permits to 90 days and tying every renewal to real progress on the repair work the shed is protecting.

In early 2026, DOB stopped auto-renewing shed permits in DOB NOW, and each renewal now carries a $130 fee. In August 2026, DOB adopted its implementing rule, 1 RCNY §102-07. It added the progress report requirement, a $90 report fee, and the penalty, waiver and challenge procedures.

90 daysMaximum term of a sidewalk shed permit
$220Total DOB fees per renewal where a progress report is required
180 daysAfter which graduated monthly penalties can apply without progress

Which Sheds Are Covered?

  • Sheds for facade work, including Local Law 11 / FISP repairs (Local Law 51 adds milestone penalties for these).
  • Sheds for other repairs and alterations, including work that does not otherwise need a permit.
  • Existing sheds: the requirements apply beginning with the second renewal of a permit issued after January 12, 2026, regardless of when the shed first went up.
Not covered: sheds installed in connection with New Building, Enlargement or Demolition work that has an issued permit. Sheds for one- and two-family homes are also excepted from the progress requirements.

What the RDP Progress Report Must Show

The report is prepared by a New York State licensed P.E. or R.A. after examining the building. In plain terms, it must answer three questions for DOB:

01

What’s been done

Work completed on the underlying repair since the last renewal.

02

What’s in progress

Work currently underway, documented with labeled photographs of the conditions.

03

When it will finish

The anticipated completion date, and with the initial report, a schedule of milestones expected at each 90-day renewal point.

Separately, the permit holder (or contractor) keeps a work progress log, updated at least weekly, which supports the report and DOB review.

Renewing a Shed Permit: Step by Step

  1. Track the 90-day expiration. Shed permits no longer auto-renew, so build the renewal date into your project calendar.
  2. Keep the work progress log current. Weekly entries make the renewal report straightforward and defensible.
  3. RDP examines the building. The engineer or architect verifies the conditions and the progress made since the last renewal.
  4. Report prepared, signed and sealed. Includes completed work, work in progress, photos and the expected completion.
  5. Renewal filed in DOB NOW. The progress information is submitted with the renewal and the fees are paid.
  6. Repeat every 90 days until the repair is complete and the shed can come down.

Fees and Penalties

ItemAmount / effect
Renewal fee$130 per renewal
Progress report fee$90 per renewal where a report is required (since Aug. 17, 2026)
No work in progressPenalties under LL48 based on the length of the shed for each month work was not in progress
Long-standing shedsGraduated monthly penalties after 180 days, which can be paused when meaningful progress is shown
LL11 / FISP facadesAdditional LL51 penalties for missed repair milestones

Penalty amounts depend on shed length, duration and milestone status. Waiver and challenge procedures are set out in 1 RCNY §102-07.

Owner Checklist

Know your datesPermit issue date, 90-day expiration, and your next renewal.
Have an RDP lined upDon’t wait until the week the permit expires.
Keep the log weeklyMake sure your contractor updates the work progress log.
Keep work movingPenalties target sheds with no work behind them.
Set real milestonesBuild a repair schedule you can actually meet at each renewal.
Plan the removalKnow what must be completed for the shed to come down.

RDP Examinations

A P.E. examines the building and verifies progress before each renewal.

Sealed Renewal Reports

DOB-ready reports with labeled photos, milestone schedules and completion dates.

Filing Support

Renewal filings, scaffold and CD-5 permits, and facade repair coordination.

Shed permit coming up for renewal?Request an RDP Report(718) 838-8187

This guide is general information about NYC requirements as of November 2026 and is not legal advice. Requirements are confirmed for each project against current laws and DOB rules.

Service Area

Sidewalk Shed RDP Reports Across NYC

FAQ

Sidewalk Shed Rules: Common Questions

How long is a sidewalk shed permit valid in NYC?

Sidewalk shed permits are now issued for a maximum of 90 days and no longer renew automatically in DOB NOW. Each renewal must be filed and paid for.

Who can prepare the sidewalk shed progress report?

A Registered Design Professional: a New York State licensed Professional Engineer or Registered Architect.

What does a sidewalk shed renewal cost?

Each renewal carries a $130 renewal fee. Where a progress report is required, a $90 progress report fee also applies, for a total of $220 per renewal.

Do the new rules apply to sheds that were already up?

Yes. The progress requirements apply beginning with the second renewal of a shed permit issued after January 12, 2026, regardless of when the shed was first installed.

Are any sheds exempt?

Sheds installed in connection with New Building, Enlargement or Demolition work with an issued permit are not subject to the progress requirements. Sheds for one- and two-family homes are also excepted.

What happens if no work is being done behind the shed?

The owner can face penalties for months in which work was not in progress, and graduated monthly penalties after 180 days, which can be paused when meaningful progress is demonstrated.

What is the work progress log?

A log kept by the permit holder, or the contractor where there is no separate permit holder, updated at least weekly to record the work being performed.