2026 Rules at a Glance
What Changed for Sidewalk Sheds
For years, a sidewalk shed permit could simply be renewed each year while the shed stayed up and little work happened behind it. The “Get Sheds Down” package changed that. Local Laws 48 and 51 of 2025 took effect on January 12, 2026, cutting shed permits to 90 days and tying every renewal to real progress on the repair work the shed is protecting.
In early 2026, DOB stopped auto-renewing shed permits in DOB NOW, and each renewal now carries a $130 fee. In August 2026, DOB adopted its implementing rule, 1 RCNY §102-07. It added the progress report requirement, a $90 report fee, and the penalty, waiver and challenge procedures.
Which Sheds Are Covered?
- Sheds for facade work, including Local Law 11 / FISP repairs (Local Law 51 adds milestone penalties for these).
- Sheds for other repairs and alterations, including work that does not otherwise need a permit.
- Existing sheds: the requirements apply beginning with the second renewal of a permit issued after January 12, 2026, regardless of when the shed first went up.
What the RDP Progress Report Must Show
The report is prepared by a New York State licensed P.E. or R.A. after examining the building. In plain terms, it must answer three questions for DOB:
What’s been done
Work completed on the underlying repair since the last renewal.
What’s in progress
Work currently underway, documented with labeled photographs of the conditions.
When it will finish
The anticipated completion date, and with the initial report, a schedule of milestones expected at each 90-day renewal point.
Separately, the permit holder (or contractor) keeps a work progress log, updated at least weekly, which supports the report and DOB review.
Renewing a Shed Permit: Step by Step
- Track the 90-day expiration. Shed permits no longer auto-renew, so build the renewal date into your project calendar.
- Keep the work progress log current. Weekly entries make the renewal report straightforward and defensible.
- RDP examines the building. The engineer or architect verifies the conditions and the progress made since the last renewal.
- Report prepared, signed and sealed. Includes completed work, work in progress, photos and the expected completion.
- Renewal filed in DOB NOW. The progress information is submitted with the renewal and the fees are paid.
- Repeat every 90 days until the repair is complete and the shed can come down.
Fees and Penalties
| Item | Amount / effect |
|---|---|
| Renewal fee | $130 per renewal |
| Progress report fee | $90 per renewal where a report is required (since Aug. 17, 2026) |
| No work in progress | Penalties under LL48 based on the length of the shed for each month work was not in progress |
| Long-standing sheds | Graduated monthly penalties after 180 days, which can be paused when meaningful progress is shown |
| LL11 / FISP facades | Additional LL51 penalties for missed repair milestones |
Penalty amounts depend on shed length, duration and milestone status. Waiver and challenge procedures are set out in 1 RCNY §102-07.
Owner Checklist
RDP Examinations
A P.E. examines the building and verifies progress before each renewal.
Sealed Renewal Reports
DOB-ready reports with labeled photos, milestone schedules and completion dates.
Filing Support
Renewal filings, scaffold and CD-5 permits, and facade repair coordination.
This guide is general information about NYC requirements as of November 2026 and is not legal advice. Requirements are confirmed for each project against current laws and DOB rules.